Log in Subscribe

Short work

Council ok’s two change orders

Posted

Meeting in special session Monday evening, the Purcell city council made short work of a brief agenda.

A $73,220 change order from Orr Construction was approved on a 3-2 vote. Dissenting votes were by Jay Tate and Allen Eubanks.

The change order covers a modification in the concrete slab at the Canadian Avenue lift station project.

The change was necessary because of groundwater elevation.

Also approved was a change order from Waldrop Construction for surgical light hanging at the new hospital.

Waldrop withdrew a second change order on the agenda for remobilization and landscaping at the new hospital.